By Hamza Faisal
Google is taking direct control of an unfinished data center campus in southeastern Wyoming that AI infrastructure developer Crusoe had been building, Crusoe confirmed on Friday, turning a failed sales pitch into one of the largest single-site bets of the AI buildout.
Google did not disclose what it paid for the site. A day earlier, the company announced plans to invest $17 billion to develop the campus in Laramie County, its first data center in Wyoming, alongside partners Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital.
From prospective tenant to owner
Crusoe had tried and failed to land Google as a customer for the Wyoming project. Google is now taking over development itself after reportedly raising concerns about the cost and construction timeline under Crusoe's management.
Bloomberg first reported the planned sale in June. The setback did not slow Crusoe down: the Denver-based company went on to raise a $3.9 billion Series F round in September at a valuation of about $30.9 billion.
Crusoe originally announced the site last year with Blackstone-backed infrastructure company Tallgrass, with plans to eventually scale it to 10 gigawatts of power capacity. Whether Google keeps that target, or Tallgrass's role in the project, has not been made public.
A $17 billion bet on power, not just servers
Google said it will pay for 100 percent of the power the site uses, and that the campus will be air-cooled to limit local water demand, two of the most sensitive issues for communities hosting large data centers.
The project is also contracted with American Electric Power for a commercial-scale, 702-megawatt fuel-cell build with carbon capture and storage, described as the largest planned development of its kind so far. The fuel cells are meant to supply firm power while the grid catches up with demand.
The deal underlines how the AI infrastructure race has moved beyond chips. With the largest models now constrained as much by electricity, water and construction timelines as by hardware, the biggest buyers are increasingly taking sites in-house rather than relying on third-party developers to deliver them.
Crusoe keeps building for Google elsewhere
The Wyoming sale does not end the relationship between the two companies. Crusoe said it remains the developer of Google's data center campus under construction near Amarillo, Texas.
Crusoe is also building a campus in Abilene, Texas, in phases for Oracle and OpenAI, and a separate 900-megawatt campus next door for Microsoft, with its first building expected to come online in mid-2027.
For Google, owning the Wyoming site outright removes a layer between it and the construction schedule. For Crusoe, the sale frees capital and attention for the projects it is still building, even as it hands its most ambitious campus to the customer it once hoped to sign.