By Hamza Faisal

Anthropic has agreed to pay about $3.4 billion for gas-fired generators to power its data centres, the Financial Times reported on Sunday, in what the paper described as the largest known single purchase of power-generation equipment by an artificial intelligence lab.

The Claude maker bought commitments for 1.7 gigawatts of heavy-duty generators in late September from OnePWR Solutions, a San Antonio, Texas-based equipment supplier, according to the report. The deal also covers the engineering and construction work needed to install the generators. Anthropic did not buy OnePWR itself, and none of the supplier's employees are moving to the AI company.

Neither Anthropic nor OnePWR commented on the report, and Reuters said it could not immediately verify it.

A shortcut around years-long equipment queues

The purchase is a shortcut around one of the AI industry's tightest bottlenecks. The generators were originally ordered by OnePWR from Caterpillar about two years ago, and Anthropic first planned to simply buy power from the supplier before deciding to take over the generator orders directly. That gives the company access to equipment available in the near term and over the next two years, rather than waiting on new manufacturing orders.

Anthropic's own IPO prospectus warns that generators and other equipment "must be ordered years in advance" and that turbines, generators, substations and transmission parts have faced "extended delivery timelines, price increases, tariffs" as data centre operators compete for them.

Power is now part of the AI race

The deal fits a wider pattern: leading AI labs are increasingly buying their own electricity infrastructure instead of relying on partners. Anthropic's amended IPO filing, published on November 2, says some of its planned data centre facilities rely on dedicated on-site natural gas-fired generation, and puts its compute and infrastructure commitments at about $895 billion through 2045.

The company filed publicly for its Nasdaq listing on October 26 and is preparing for a possible public listing as early as November 2026, though market turbulence has pushed valuation expectations down to between $1 trillion and $1.3 trillion, according to recent reports.

The energy bill behind the AI boom

The generator purchase comes as the industry's power demands keep climbing. Google announced a $17 billion Wyoming data centre earlier this month, and data centre projects across the United States and Europe have drawn protests over electricity use and local opposition. For Anthropic, owning the generators outright is a bet that controlling its power supply matters as much as securing chips.

Securing 1.7 gigawatts of generation in a single stroke also underlines how far the AI buildout has moved from software into heavy industry. The race is no longer only about who trains the smartest model. It is about who can keep the lights on while training it.