Thousands of people marched through Edinburgh on Saturday to protest against plans for large-scale AI data centres across Scotland, in one of the biggest public demonstrations yet against the industry's breakneck expansion. Demonstrators gathered at the top of the Royal Mile before marching to the Scottish Parliament, carrying placards and wearing costumes, as campaigners demanded the public get a say before any of the projects are approved.

A national conversation — or a pause?

Organisers said around 6,000 people joined the march, according to Friends of the Earth Scotland senior campaigner Kim Pratt, though no police estimate was published. More than 80 organisations backed the demonstration, including climate campaigners, trade unions, community groups and anti-poverty charities.

The campaigners want the Scottish government to pause approvals and open a "national conversation" on the data-centre buildout, arguing ministers have "failed to explain" why Scotland needs the facilities. Some are calling for an outright moratorium until the public has been consulted.

Their concerns centre on energy and the environment. Twenty-three proposals for hyperscale AI data centres are at various stages of planning across Scotland, each between 125 and 1,000 megawatts, adding up to 7.3 gigawatts of demand, according to evidence given to Holyrood's Climate Action Committee. Friends of the Earth Scotland estimates the full pipeline could add 9.1 gigawatts against a current peak demand of about 5 gigawatts.

Chapelcross, the flashpoint

The most contentious site is Chapelcross in Dumfries and Galloway, where a proposed facility could reach 1,000 megawatts — a plan that has already drawn more than 10,000 objections. Campaigner Kim Cairns, from Say No To Chapelcross AI Data Centre, told BBC Scotland News that residents feared noise, road closures and access problems during construction, as well as the long-term impact of the facility.

By contrast, Scotland's largest existing data centre is DataVita's 12-megawatt site in Airdrie — dwarfed by the scale of what is proposed. Other sites drawing concern include Cockenzie in East Lothian and Larbert in Falkirk.

Government defends the buildout

The Scottish government says it will publish new planning guidance on data centres before the end of the year and is developing a strategy to maximise the "public benefit" of the developments. Innovation Minister Alyn Smith has defended the sector, describing data centres as "the whisky bonds of the AI sector" and dismissing some of the criticism as "wild".

The Edinburgh march was part of a Europe-wide wave of protests against data centres, with more than 70 demonstrations across 15 countries this month. As AI's appetite for power keeps growing, the fight over where — and whether — to build the infrastructure behind it is moving from planning offices into the streets.