Oracle said on Friday that its infrastructure contract with OpenAI is fully funded, closing weeks of investor debate over how the software giant will pay for one of the largest data-centre buildouts in the industry's history.
The company made the announcement in a post on X, saying the financing it outlined at its Investor Day — including vendor financing — is now in place. Shares rose as much as 3.3% in after-hours trading after the update.
The statement lands after a bruising stretch for Oracle's stock. Investors have spent weeks questioning whether the company can afford the enormous capital spending tied to its OpenAI work, as the broader AI rally wobbles and the S&P 500 slides into correction territory.
The $20 billion raise that closed the gap
Oracle said the deal is covered following its final capital raise earlier this month — a $20 billion package made up of about $10 billion in stock and $10 billion in debt. The company described itself as the first hyperscaler to be fully funded for the current investment cycle.
"The financing we outlined at Oracle Investor Day, including vendor financing, is in place. Any further private discussions with vendors are just additional options," Oracle said in the post.
Oracle also repeated its target of generating more than $30 billion in free cash flow in its 2029 fiscal year, and said it expects to begin funding future growth from its own cash from that year onward.
Abilene nearly done, Shackelford permitted
The company gave a progress report on the physical buildout behind the deal. Its campus in Abilene, Texas — where OpenAI's GPT-6 Astra model was trained — is nearly complete, Oracle said.
Oracle and OpenAI plan to develop 4.5 gigawatts of additional data-centre capacity in the United States on top of the initial Stargate site in Abilene. The next gigawatt-scale campus, in Shackelford County, Texas, is now fully permitted.
The handover of Nvidia's next-generation Vera Rubin server racks into Oracle's data halls is on track to begin in the coming weeks, the company added.
Why investors were worried
The reassurance matters because the scale of Oracle's commitments is extraordinary. The five-year computing agreement with OpenAI has been reported at about $300 billion, and Oracle's remaining performance obligations have swelled as the Stargate programme has grown.
That growth has come with scrutiny. Analysts and investors have asked whether Oracle is taking on too much debt to chase AI infrastructure revenue, and whether OpenAI — its largest customer — can keep paying for the capacity it has reserved.
Friday's message was designed to answer both questions at once: the money is secured, the campuses are moving, and the hardware is arriving. What remains to be seen is whether the cash the data centres generate matches the forecasts Oracle has put in front of investors.