By Hamza Faisal

Fusion power's biggest bottleneck may not be the plasma. It may be the chips. Fusion startup Helion has signed a letter of intent with the US Department of Commerce for up to $175 million in federal research funding to develop advanced semiconductors and power electronics for its fusion power plants, the company announced on Thursday.

Helion plans to pair the proposed award with $50 million of its own private investment, for a combined $225 million effort. Under the proposed terms, the federal government would receive a minority, non-voting equity stake in the company. The funding is not yet final: a definitive award agreement still has to be signed.

Why chips matter to a fusion reactor

Helion's machines work differently from most fusion designs. Instead of using fusion heat to make steam and spin a turbine, its reactors heat fuel into plasma, accelerate and compress it with magnetic fields, then capture the energy released as it pushes back against those fields — converting it directly into electricity through magnets and capacitors.

That approach lives or dies on power electronics. The semiconductors and modules that switch and recover energy currently lose about 5 to 10 percent of the electricity flowing through them, and those losses compound across a complex system. "If we can cut that loss in half, that's actually twice the power output of the fusion system," co-founder and chief executive David Kirtley told TechCrunch.

Where the money goes

The funding would build automated semiconductor module, packaging and testing capacity in the United States. More than $100 million is earmarked for semiconductor and advanced-packaging research in Everett, Washington, where more than 100 jobs are expected, and about $80 million for tooling, design and process work with an industry partner in Burlington, Vermont.

The new production line, to be built in Washington state, would be the first in the US to make this class of high-voltage, pulsed semiconductor. Kirtley noted the same components are used beyond fusion — in manufacturing, wastewater treatment, medicine and defence — and said there are currently no US manufacturers making them. "This is absolutely enabling going from zero to 100 for advanced, high-voltage, and pulsed semiconductors here in the United States," he said.

The 2028 deadline

Helion is racing to complete its first power plant, Orion, in time to meet a 2028 deadline to supply Microsoft with electricity from the grid under a power purchase agreement signed in 2023, targeting at least 50 megawatts after a one-year ramp-up. The new semiconductors will not be ready for Orion itself, but are meant to boost future plants.

The award is part of a broader Commerce Department announcement: its National Institute of Standards and Technology signed letters of intent for up to $389 million in research awards across four companies. For Helion, the bet is that fixing the unglamorous electronics — not just the physics — is what turns fusion from a demonstration into an industry.