CoreWeave has switched on the majority of its planned 22.5 megawatts of IT capacity at atNorth's DEN01 data center in Copenhagen, marking its first deployment in Denmark and the latest step in the AI cloud provider's rapid expansion across Europe. The company announced the move on October 27, alongside plans to stretch its global AI network backbone into the Middle East and Asia Pacific.
The Copenhagen deployment gives CoreWeave a foothold in the Nordics' fast-growing data center market at a time when demand for AI computing continues to outrun supply. For customers in Europe and beyond, it adds another high-performance site close to home, cutting the distance their workloads must travel to reach powerful graphics processors.
Blackwell power for Copenhagen
DEN01 is accelerated by Nvidia Blackwell systems connected with Nvidia Quantum-X800 InfiniBand, the high-speed networking technology that lets thousands of graphics processors work together as a single system. That combination is built for the largest AI training and inference workloads, where slow links between chips can become the bottleneck.
The facility also has a heat reuse agreement in place to supply surplus heat to the local district heating network, reducing reliance on other heating sources and contributing to Denmark's green transition. Eyjólfur Magnús Kristinsson, chief executive of atNorth, said the site is designed for GPU-intensive processing while supporting renewable energy development through power purchase agreements and helping warm local homes through heat reuse.
A network stretching across four continents
Alongside the new capacity, CoreWeave is extending its global AI network backbone with new points of presence in the United Arab Emirates, India, Indonesia, Singapore, Australia, Korea and Japan, beginning later in the fourth quarter of 2026 and extending to a full loop in mid-2027. The expansion will take its existing network across North America and Europe into four continents, giving customers more direct connectivity to its AI cloud platform.
The backbone is built at petabit scale, with multiple 400 gigabit-per-second connections at each location and hardware-based MACsec encryption to protect data in transit. CoreWeave said it is expanding its global infrastructure and the network connecting it together so customers can focus on building and improving AI rather than managing the complexity underneath it.
Scale in an AI infrastructure race
The Copenhagen site expands CoreWeave's European footprint to nine data centers across five geographies, including the United Kingdom, Spain, Sweden and Norway. AtNorth, headquartered in Reykjavik, operates seven data centers across the Nordics and has four mega sites under development in Finland, Denmark, Sweden and Norway, plus another metro site under construction in Stockholm.
The scale of the buildout reflects how quickly AI infrastructure is growing. As of June 30, 2026, CoreWeave operated 51 data centers worldwide with more than 1.5 gigawatts of active power, and it reported approximately 4.2 gigawatts of contracted power during its August 11 earnings call. With the Denmark launch and the new intercontinental backbone, the company is betting that customers will pay for capacity that is both closer to them and easier to reach.